Moreton Bay · South East Queensland · DA statistics

Townhouse development in Redcliffe: approval rates, timelines and costs

Real outcomes from 28 decided multiple-dwelling and multi-unit applications on Redcliffe properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 28 decided applications in Moreton Bay, 100% of townhouse development applications in Redcliffe were approved, with a median decision time of 99 days.

100%

Approval rate

28 of 28 decided applications

99 days

Median decision time

Lodgement to decision (n=28)

28

Decided applications

Comparable multiple-dwelling and multi-unit applications

14 Jan 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Redcliffe

Across 28 decided multiple-dwelling and multi-unit applications on Redcliffe properties, 28 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 99 days (measured across the 28 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 28 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Redcliffe

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/5775Approved14 Jan 202661 days
DA/2025/3688Approved6 Oct 202562 days
DA/2025/2612Approved22 Sept 2025105 days
DA/2025/2946Approved29 July 202534 days
DA/2025/2436Approved16 July 202548 days

About this data

These statistics summarise decided development applications recorded against Redcliffe properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.