Brisbane · South East Queensland · DA statistics
Subdividing in Seven Hills: approval rates, timelines and costs
Real outcomes from 179 decided reconfiguration and subdivision applications on Seven Hills properties, drawn from Brisbane council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 179 decided applications in Brisbane, 97% of subdivision applications in Seven Hills were approved, with a median decision time of 50 days.
97%
Approval rate
173 of 179 decided applications
50 days
Median decision time
Lodgement to decision (n=179)
179
Decided applications
Comparable reconfiguration and subdivision applications
16 Apr 2026
Latest decision
Most recent decided application in this cohort
What the numbers say about Seven Hills
Across 179 decided reconfiguration and subdivision applications on Seven Hills properties, 173 were approved — an approval rate of 97%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.
The median time from lodgement to decision was 50 days (measured across the 179 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 179 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Seven Hills
The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| A006902453 | Approved | 16 Apr 2026 | 150 days |
| A006914161 | Approved | 17 Mar 2026 | 105 days |
| A006846619 | Approved | 28 Oct 2025 | 63 days |
| A005906368 | Approved | 16 Oct 2025 | 1399 days |
| A006835074 | Approved | 19 Sept 2025 | 39 days |
About this data
These statistics summarise decided development applications recorded against Seven Hills properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.