Brisbane · South East Queensland · DA statistics

Unit development in Seven Hills: approval rates, timelines and costs

Real outcomes from 15 decided multiple-dwelling and multi-unit applications on Seven Hills properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 15 decided applications in Brisbane, 100% of unit development applications in Seven Hills were approved, with a median decision time of 226 days.

100%

Approval rate

15 of 15 decided applications

226 days

Median decision time

Lodgement to decision (n=15)

15

Decided applications

Comparable multiple-dwelling and multi-unit applications

26 Nov 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Seven Hills

Across 15 decided multiple-dwelling and multi-unit applications on Seven Hills properties, 15 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 226 days (measured across the 15 applications in this cohort with both dates recorded). That is a longer-than-typical assessment timeframe — worth building into your project programme. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 15 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Seven Hills

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006831264Approved26 Nov 2025112 days
A006721490Approved18 July 2025140 days
A006522441Approved16 Apr 2025338 days
A005888953Approved21 Apr 2023513 days
A005985545Approved13 Apr 2023371 days

About this data

These statistics summarise decided development applications recorded against Seven Hills properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.