Moreton Bay · South East Queensland · DA statistics

Subdividing in Wamuran: approval rates, timelines and costs

Real outcomes from 14 decided reconfiguration and subdivision applications on Wamuran properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 14 decided applications in Moreton Bay, 93% of subdivision applications in Wamuran were approved, with a median decision time of 76 days.

93%

Approval rate

13 of 14 decided applications

76 days

Median decision time

Lodgement to decision (n=14)

14

Decided applications

Comparable reconfiguration and subdivision applications

17 Dec 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Wamuran

Across 14 decided reconfiguration and subdivision applications on Wamuran properties, 13 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 76 days (measured across the 14 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 14 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Wamuran

The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/2868Lapsed17 Dec 2025177 days
DA/2025/3310Approved29 Aug 202545 days
DA/2024/2793Approved8 Nov 2024135 days
DA/2023/1935Approved28 Aug 202396 days
DA/2022/4943Approved15 Mar 202399 days

About this data

These statistics summarise decided development applications recorded against Wamuran properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.