According to Casa Intelligence analysis of 10 decided applications in Moreton Bay, 90% of townhouse development applications in Woodford were approved, with a median decision time of 118 days.
90%
Approval rate
9 of 10 decided applications
118 days
Median decision time
Lodgement to decision (n=10)
10
Decided applications
Comparable multiple-dwelling and multi-unit applications
21 Nov 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Woodford
Across 10 decided multiple-dwelling and multi-unit applications on Woodford properties, 9 were approved — an approval rate of 90%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 118 days (measured across the 10 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 10 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Woodford
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2025/5359 | Approved | 21 Nov 2025 | 25 days |
| DA/2024/5887 | Lapsed | 12 Aug 2025 | 237 days |
| DA/2024/5138 | Approved | 14 May 2025 | 187 days |
| DA/2023/4720 | Approved | 31 Mar 2025 | 494 days |
| DA/2024/4282 | Approved | 3 Jan 2025 | 101 days |
About this data
These statistics summarise decided development applications recorded against Woodford properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.