Logan · South East Queensland · DA statistics
Building a duplex in Kingston: approval rates, timelines and costs
Real outcomes from 66 decided dual-occupancy and multi-unit dwelling applications on Kingston properties, drawn from Logan council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 66 decided applications in Logan, 96% of duplex and dual-occupancy applications in Kingston were approved, with a median decision time of 39 days.
96%
Approval rate
63 of 66 decided applications
39 days
Median decision time
Lodgement to decision (n=65)
66
Decided applications
Comparable dual-occupancy and multi-unit dwelling applications
4 July 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Kingston
Across 66 decided dual-occupancy and multi-unit dwelling applications on Kingston properties, 63 were approved — an approval rate of 96%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 39 days (measured across the 65 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 66 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Kingston
The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCUR/65/2025 | Approved | 4 July 2025 | 2 days |
| MCUR/314/2022 | Approved | 26 Mar 2025 | 27 days |
| MCUC/65/2024 | Approved | 2 Dec 2024 | 181 days |
| MCUC/46/2024 | Approved | 29 Oct 2024 | 200 days |
| MCUC/71/2023 | Approved | 6 June 2024 | 371 days |
About this data
These statistics summarise decided development applications recorded against Kingston properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.