Logan · South East Queensland · DA statistics

Building a duplex in Park Ridge: approval rates, timelines and costs

Real outcomes from 100 decided dual-occupancy and multi-unit dwelling applications on Park Ridge properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 100 decided applications in Logan, 89% of duplex and dual-occupancy applications in Park Ridge were approved, with a median decision time of 49 days.

89%

Approval rate

89 of 100 decided applications

49 days

Median decision time

Lodgement to decision (n=100)

100

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

9 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Park Ridge

Across 100 decided dual-occupancy and multi-unit dwelling applications on Park Ridge properties, 89 were approved — an approval rate of 89%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 49 days (measured across the 100 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 100 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Park Ridge

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCUR/100/2025Approved9 Feb 2026147 days
MCUR/129/2025Approved14 Jan 202658 days
MCUR/108/2025Approved8 Jan 2026105 days
MCUR/122/2025Approved8 Jan 202673 days
MCUR/120/2025Approved16 Dec 202554 days

About this data

These statistics summarise decided development applications recorded against Park Ridge properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.