Logan · South East Queensland · DA statistics

Building a duplex in Marsden: approval rates, timelines and costs

Real outcomes from 148 decided dual-occupancy and multi-unit dwelling applications on Marsden properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 148 decided applications in Logan, 93% of duplex and dual-occupancy applications in Marsden were approved, with a median decision time of 31 days.

93%

Approval rate

137 of 148 decided applications

31 days

Median decision time

Lodgement to decision (n=145)

148

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

17 Oct 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Marsden

Across 148 decided dual-occupancy and multi-unit dwelling applications on Marsden properties, 137 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 31 days (measured across the 145 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 148 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Marsden

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
COM/33/2019Approved17 Oct 202545 days
COM/33/2019Approved17 Oct 202518 days
MCUR/92/2025Approved15 Oct 202557 days
MCUI/11/2010Approved17 Sept 2025112 days
MCUR/44/2025Approved13 Aug 2025103 days

About this data

These statistics summarise decided development applications recorded against Marsden properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.