Logan · South East Queensland · DA statistics

Building a duplex in Meadowbrook: approval rates, timelines and costs

Real outcomes from 8 decided dual-occupancy and multi-unit dwelling applications on Meadowbrook properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 8 decided applications in Logan, 88% of duplex and dual-occupancy applications in Meadowbrook were approved, with a median decision time of 31 days.

88%

Approval rate

7 of 8 decided applications

31 days

Median decision time

Lodgement to decision (n=7)

8

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

19 Apr 2024

Latest decision

Most recent decided application in this cohort

What the numbers say about Meadowbrook

Across 8 decided dual-occupancy and multi-unit dwelling applications on Meadowbrook properties, 7 were approved — an approval rate of 88%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 31 days (measured across the 7 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 8 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Meadowbrook

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCUR/44/2024Approved19 Apr 202431 days
MCUC/443/2017Approved3 Nov 201730 days
MCUC/35/2016Withdrawn3 Mar 201627 days
COM/35/2014Approved24 Feb 2016436 days
MCUC/65/2007Approved12 Dec 201338 days

About this data

These statistics summarise decided development applications recorded against Meadowbrook properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.